3/9/17 H.E. Hill West Tech Cabinet Building Construction Academy (first cabinets produced by this Academy in Belle Glade, FL)
2/3/17 Install Day (same crew, trucks, and crane as on Load Day)
2/2/17 Load Day (7 tractor-trailers from Priority Towing & American Engineering, 10 workers from Weitz Const. Co., and a crane with operator from Precision Crane & Rigging: All donated)
1/27/17 Ready to Ship to site
1/25/17 Foundation block installed; concrete cap formed
size=”thumbnail”
1/12/17 Grade Beam formed and ready for concrete
1/15/17 Helical Piling installed of grade beam forms at the site
Siding Completed and Ready for Painting (12/14/16)
Drywall completed; siding & interior painting underway (10/24/16)
Windows installed & insulation is complete (9/21/16)
Building wrap & start of insulation (9/13/16)
Electrical and Plumbing Rough-in completed (2 weeks time) 9/8/16
Wall studs completed; wall sheathing done; ceiling joists installed (5/20/16; end of 2015-16 school year)
Wall studs up on modules (5/4/16)
Dry-in complete & roof sections stored outside (4/20/16)
Roof sheathing installed in shop (4/6/16)
Trusses all assembled in shop (3/17/16)
Floor sheathing installed (2/25/16)
Floor joists installed (2/11/16)
Floor framing lumber arrives (2/3/16)
New Test Gallery