Foundation completed 12/6/2024
Floor framing completed 12/10/2024
Floor sheathing completed 1/7/2025
Roof trusses completed 2/6/2025
Roof sheathing completed 2/27/2025
Exterior walls framed 4/1/2025
Exterior walls sheathing; start windows installation 4/25/2025
Plumbing and Electrical Rough-in stage; Windows & Doors Installed 10/14/2025
Wall insulation completed 10/17/2025
Drywall installed 11/04/2025