The photos below show the start-to-finish of the student builders’ work & the moving in by the owner.  Click on a photo to see the enlarged version.

Owner’s personalized interior touches to make the house a home (4/24/13)

House completion & dedication; Tina takes ownership (2/22/13)

The completed house, ready for the dedication and turning over the keys to Tina

Home’s owner is chosen by Habitat

Porch built, module connection trim, siding started, electrical wiring connections (12/7/12); this work completed by Habitat

AC installation completed by Royal Palm Beach HS Air Conditioning Academy students (12/6/12)

Dwyer HS Construction Academy begin back shed construction (11/17/12)

Moving & Installation Day (11/14/12: 6 AM until 5 PM)

Construction complete; Loading Day (11/13/12: 8:30 AM until 2 PM)

Cabinets installed, roller test, electrical testing (11/5/12)

Robert Trepp of Cardinal Electric worked with students to test out all final electrical and lighting connections.  All worked flawlessly without any corrections needed.

Foundation blockwork laid (11/3/12)

Concrete work and blockwork supervision provided by John Elliott and his crew from All Phase, Inc. The blockwork was installed by 6 apprentices from the Florida Masonry Apprentice & Educational Foundation of Palm Beach County.

Footings reinforced & ready to pour concrete (10/31/12)

Foundation work started (10/24/12)

Assembly of roof sections started (10/15/12)

Interior doors & trim done; all interior painted (10/15/12)

Knock-down texture applied (10/11/12)

Lot has been cleared (10/9/12)

Ceiling drywall hung; all drywall finishing done; interior doors & trim started (9/21/12)

Drywall finishing on walls in progress (5/31/12)

Drywall on walls almost all hung; shower & tub installed (5/10/12)

Insulation installation; windows sealed; exterior door installed (5/2/12)

AC cans roughed in by Royal Palm Beach HS AC Academy (5/1/12)

Final rough-in (plumbing & electrical); Blueskin underlayment (4/20/12)

Sheathing finished; plumbing & electrical rough about ready for inspection (3/30/12)

Electrical & Plumbing Rough Started (2/22/12)

Walls and Ceiling Framing completed (2/10/12)

Exterior walls framing (12/16/11)

Installation of the floor insulation (10/14/11)

Start of Floor Joists Installation (9/16/11)

The Shop and The Beginning (8/30/11)