2024 #11 South Bay

Floor framing started 9/5/2023

 

Floor framing completed 9/13/2023

 

Floor sheathing completed 9/27/2023

 

Roof trusses started 10/6/2023

 

Roof trusses assembled 10/25/2023

 

Roof sheathing 11/10/2023

       

 

Roof underlayment completed 11/15/2023

 

Exterior walls framed 01/17/2024

 

Exterior wall sheathing 01/29/2024

 

Mechanical & Electrical Rough-In 03/15/2024

 

Insulation, Windows, and Doors 04/5/2024

 

Drywall installed 05/13/2024

 

Foundation started at site by Habitat 09/18/24

 

Interior painted; Durock underlayment installed; ready to ship 11/13/24

 

Load Day at school 12/05/24

 

Install Day at the site 12/06/24