Floor framing started 9/5/2023
Floor framing completed 9/13/2023
Floor sheathing completed 9/27/2023
Roof trusses started 10/6/2023
Roof trusses assembled 10/25/2023
Roof sheathing 11/10/2023
Roof underlayment completed 11/15/2023
Exterior walls framed 01/17/2024
Exterior wall sheathing 01/29/2024
Mechanical & Electrical Rough-In 03/15/2024
Insulation, Windows, and Doors 04/5/2024
Drywall installed 05/13/2024
Foundation started at site by Habitat 09/18/24
Interior painted; Durock underlayment installed; ready to ship 11/13/24
Load Day at school 12/05/24