The photos below show the start-to-finish of the student builders’ work & the moving in by the owner. Click on a photo to see the enlarged version.
Owner’s personalized interior touches to make the house a home (4/24/13)
- Back corner of living room as completed by the students
 
- Back corner of living room decorated by owner
 
- Front corner of living room completed by the students
 
- Front corner of living room as decorated by owner
 
- Kitchen as completed by students
 
- Kitchen with the owner’s special touches
 
- Another view of owner’s customization of the kitchen
 
House completion & dedication; Tina takes ownership (2/22/13)
- The completed house
 
- Dedication program
 
- Seniors stand on the porch of their creation
 
- Seniors & juniors stand proud at their creation
 
- Students present signed plywood panel to Tina
 
- Academy teacher, Rick Terkovich
 
- Tina cutting the ceremonial ribbon
 
- Ernie presents keys to Tina
 
The completed house, ready for the dedication and turning over the keys to Tina
- Completed house
 
Home’s owner is chosen by Habitat
- Lisa Cromatie opening the door to her new house for the first time
 
- Team members with the new owner (David Porter- Architect, student builder, Bernard Godek- Exec. Dir. of Habitat PBC, owner Lisa Cromatie, and Rick Terkovich – Academy instructor
 
Porch built, module connection trim, siding started, electrical wiring connections (12/7/12); this work completed by Habitat
- Rough construction for porch completed
 
- Wires roughed in by students pulled into shed
 
- Shed completed by Habitat
 
- Siding installation underway
 
- It’s coming together nicely
 
- Trim at module connection joints started
 
AC installation completed by Royal Palm Beach HS Air Conditioning Academy students (12/6/12)
- Air handler installed and piped
 
- Ductwork neatly installed in attic
 
- Ductwork in attic
 
- AC compressor pad set and refrigerant piping run through crawlspace from AHU to pad
 
Dwyer HS Construction Academy begin back shed construction (11/17/12)
Moving & Installation Day (11/14/12: 6 AM until 5 PM)
- 6:09 AM; first trailer & module leave the school
 
- First module turning into it’s neighborhood home
 
- Crawlspace foundation anxiously awaits its home
 
- Master BR module being lifted into place
 
- Setting MBR module onto foundation
 
- Kitchen module fitting perfectly onto foundation
 
- Roof section lifted from trailer
 
- Roof section coming in for permanent landing
 
- Roof sections in place on top of modules
 
- Kitchen module seeing daylight for first time
 
- Modules joined as a complete house for first time
 
- 5 PM; house all assembled & water tight
 
- A successful conclusion to the students work
 
Construction complete; Loading Day (11/13/12: 8:30 AM until 2 PM)
- Roof section lifted for loading
 
- Roof section onto trailer
 
- First module squeezing out the door
 
- It fits !!!! (yeah, we knew that all along)
 
- Keep coming
 
- Almost out
 
- It’s Out !!! and ready for lifting
 
- Modules on rollers easily pushed out the door with student power
 
- Loading onto a trailer
 
- Loading continues until 7 trailers are filled
 
Cabinets installed, roller test, electrical testing (11/5/12)
Robert Trepp of Cardinal Electric worked with students to test out all final electrical and lighting connections. All worked flawlessly without any corrections needed.
- Kitchen cabinets completed
 
- Bathroom vanity cabinet & light installed
 
- Roof section fabricated
 
- Roof section dried in
 
- Rollers to be used to roll the modules out the door
 
- 4 students easily pushed the modules along the slab
 
Foundation blockwork laid (11/3/12)
Concrete work and blockwork supervision provided by John Elliott and his crew from All Phase, Inc. The blockwork was installed by 6 apprentices from the Florida Masonry Apprentice & Educational Foundation of Palm Beach County.
Footings reinforced & ready to pour concrete (10/31/12)
Foundation work started (10/24/12)
Assembly of roof sections started (10/15/12)
Interior doors & trim done; all interior painted (10/15/12)
Knock-down texture applied (10/11/12)
- Student builder knocking down spray applied compound on wall
 
- Student builder knocking down spray applied compound on ceiling
 
- Knock down finish completed
 
Lot has been cleared (10/9/12)
- Looking from street toward back of lot
 
- Looking from back of lot toward street
 
Ceiling drywall hung; all drywall finishing done; interior doors & trim started (9/21/12)
Drywall finishing on walls in progress (5/31/12)
Drywall on walls almost all hung; shower & tub installed (5/10/12)
Insulation installation; windows sealed; exterior door installed (5/2/12)
AC cans roughed in by Royal Palm Beach HS AC Academy (5/1/12)
Final rough-in (plumbing & electrical); Blueskin underlayment (4/20/12)
Sheathing finished; plumbing & electrical rough about ready for inspection (3/30/12)
Electrical & Plumbing Rough Started (2/22/12)
Walls and Ceiling Framing completed (2/10/12)
Exterior walls framing (12/16/11)
- Exterior walls framing 1
 
- Exterior walls framing 2
 
- Exterior walls framing 4
 
- Exterior walls framing 4
 
- Exterior walls framing 5
 
- Exterior walls framing 6
 
- Exterior walls framing 7
 
- Exterior walls framing 8
 
- Exterior walls framing in progress
 
- Exterior walls framing in progress
 
- Exterior walls framing in progress 3
 
Installation of the floor insulation (10/14/11)
- Floor insulation installed in all modules
 
- Floor insulation
 
- Floor insulation close-up
 
Start of Floor Joists Installation (9/16/11)
- Floor joists layout
 
- Students at work on the floor joists
 
- Observation of work by contractors & mentors
 
The Shop and The Beginning (8/30/11)
- The Shop and rim board layout for all 4 modules
 
- Inside view of the shop door the modules will exit through
 
- The modules will make it out the door with 2 1/2″ to spare
 
- Rim boards layout
 
	
	
				
	






































































































































































